New outlet works
A new control tower, connecting tunnel and stilling basin are planned on the dam’s left abutment. The existing tower is to be retired after the new system becomes operational.
← Lake conditionsOfficial-source project guide
What Phase 2 and the 490-foot summer-pool target mean for residents, homeowners and people planning a lake day.
Last reviewed September 8, 2026Latest reviewed milestone
USACE awarded the Phase 2 contract in December 2025 and says the main construction phase is expected to take approximately six to eight years.
Official milestone announcement ↗The work
The project is intended to provide permanent risk reduction for downstream communities.
A new control tower, connecting tunnel and stilling basin are planned on the dam’s left abutment. The existing tower is to be retired after the new system becomes operational.
USACE plans a cutoff wall across the dam crest, varying from about 75 to 180 feet deep, to address risk associated with the foundation and karst geology.
The final portion of Phase 2 includes moving Kentucky Highway 79 back to the top of the dam.
Why it is happening
The project follows an evaluation that identified unacceptable risk connected to the dam foundation and its karst geology. Phase 1 reduced risk through drilling, grouting and relocation of the crest road. USACE says continued monitoring showed ongoing foundation deterioration, making Phase 2 necessary for permanent risk reduction.
Read the official project overview ↗Daily work schedules, blasting dates, closures, a guaranteed completion year, future changes to lake operations or whether a particular dock will remain usable.
Lake operations
USACE identifies 490 feet as the current interim summer-pool target until long-term repairs are complete. The agency also describes a delayed seasonal fill beginning around April 1 rather than March 15.
The measures are reviewed annually and can be adjusted when necessary. That makes 490 feet the current official target—not a promise that future operations can never change.
Milestones
A dam-safety evaluation identified foundation-related risk.
Phase 1 drilling, grouting and crest-road relocation were completed.
Additional interim risk-reduction measures were implemented.
USACE awarded the Phase 2 base construction contract.
USACE held a public project update meeting at the state park lodge.
The official Phase 2 groundbreaking was held.
USACE anticipates approximately six to eight years of Phase 2 construction; this is not a guaranteed completion date.
Follow the facts
Today at Rough River is not an official USACE publication. For safety decisions and the latest official status, use the linked USACE sources or contact the appropriate office directly.